Energy & utilities · Germany · Onshore wind / permit cycle

German wind developers wait 25 months for a permit — and the office that decides is short-staffed too.

Germany wants 115 gigawatts of onshore wind running by 2030 and has roughly 64 today. Every new turbine has to clear a federal pollution-and-noise licence under the Bundes-Immissionsschutzgesetz (the federal immission-control law). According to the federal wind agency that tracked the procedure from 2011 to 2022, the licence step alone now takes 25 months — almost twice the 14 months it took before 2018. Two labour pools are short: planning engineers on the developer side, case workers on the regulator side.

01The pain

Germany wants 115 gigawatts of onshore wind — turbines on land, not at sea — by 2030. It has 64. Every new turbine must clear a federal pollution-and-noise licence under the Bundes-Immissionsschutzgesetz (BImSchG, Germany's federal immission-control law). The Fachagentur Wind und Solar (the federal wind agency) tracked the procedure from 2011 to 2022. The licence step now takes 25 months, almost twice the 14 months before 2018.1

The completeness check by the Genehmigungsbehörde (the state permit office that reads the dossier) climbed from 9 to 18 months. Add four years of pre-development before the developer even files, and the average wind farm needs 50 months from first paperwork to first kilowatt-hour.2 Two labour pools are short. Developers cannot find enough planning engineers to write the bat surveys, noise models and grid studies a BImSchG dossier needs. The Regierungspräsidien (state-level case-work authorities) cannot find enough case workers to read them.3

BDEW (the German energy industry association) wants outside project managers, allowed under §2a 9. BImSchV (a 2024 rule letting private contractors draft permit decisions), to help clear the queue.4 The 2024 BImSchG-Novelle (the law's 2024 revision) wrote the role in. Uptake is slow.5 Each year a 30-megawatt project sits in the queue, it strands €200,000 to €1 million in surveys already paid, land options signed, tender awards won with a build deadline the project will miss.

25 months for a single BImSchG licence — up from 14 before 2018.
"Each year a 30-megawatt project sits in the queue strands €200,000 to €1 million — surveys paid, land options signed, tender awards won with a build deadline the project will miss." — Germany · onshore-wind developer project-finance reality · 2026

Further reading

  • 1 fachagentur-wind-solar.de — "Genehmigung von Windenergieanlagen an Land": the Fachagentur Wind und Solar (the federal wind and solar agency) page summarising the BImSchG procedure and the 2011-to-2022 cohort study that produced the 25-month and 18-month figures (German): fachagentur-wind-solar.de
  • 2 bdew.de — "Längere Verfahrenslaufzeiten von Windenergieprojekten": Bundesverband der Energie- und Wasserwirtschaft (BDEW, the German energy industry association) brief on lengthening procedure runtimes including the ~50-month total figure (German): bdew.de
  • 3 enbw.com — "Genehmigungsverfahren Windkraftanlage": EnBW (one of Germany's four large utilities) plain-language walkthrough of what a BImSchG dossier contains — bat surveys, noise models, grid-connection studies — explaining why both sides need scarce specialist staff (German): enbw.com
  • 4 bdew.de — "Bundestag beschließt BImSchG-Novelle": BDEW announcement on the 2024 amendment to the federal immission-control law that introduced §2a 9. BImSchV outside project managers (German): bdew.de
  • 5 stiftung-umweltenergierecht.de — "Urteil zur Windenergie: Behörden müssen sich an Verfahrensregeln halten": Stiftung Umweltenergierecht (an environmental-law foundation) commentary on a court ruling reinforcing procedural deadlines on Genehmigungsbehörden, evidencing that even after the 2024 reform, uptake of the new tools is patchy (German): stiftung-umweltenergierecht.de
Ad · rail 1
Your banner here
€20/ month
A Saxon developer is short one bat-survey biologist. A Hessian Regierungspräsidium has three open BImSchG case-worker postings. A staffing agency can fill both rosters. Buy the slot next to them.
"Wann kommt die Genehmigung?" — every Vorhabenträger. "Bald." — the Behörde.
Buy this ad slot →
PayPal subscription · Cancel any time · 1-month minimum
Ad · inline 1
Your banner here
€20/ month
Selling contract bat-survey biologists, BImSchG dossier engineers or §2a outside project managers? Selling permit-tracking software for German developers? Running a TR10 site-quality forecasting service or a noise-model SaaS that shaves weeks off the dossier? Your buyers are on this page right now.
Banner size: bigger than a Genehmigungsantrag binder. Faster to install than a §2a project manager.
Buy this ad slot →
PayPal subscription · Cancel any time · 1-month minimum

02Who solves this today

Five German-market vendors that publicly market themselves as solving exactly the gap the BImSchG permit cycle opens — wind site assessment and energy-yield reports for the dossier, end-to-end environmental and permit-procedure consulting, bat-and-bird surveys, and full BImSchG-application drafting. Each homepage was checked live on the date of writing. The list is intentionally narrow.

Reppenstedt-based wind-energy consultancy. Homepage markets Site Assessment, Site Quality forecasts according to TR10 (the German technical guideline for energy-yield assessment), Wind Atlas, Wind Measurements, Due Diligence and Performance reporting — the calculations a BImSchG dossier needs.
anemos.de
German arm of the Nordic engineering and management consultancy. Homepage markets Energiewende work and explicitly identifies komplexe Genehmigungsverfahren (complex permit procedures) as a bottleneck for grid and renewable build-out, with multidisciplinary teams positioned to staff developer-side dossier work.
de.ramboll.com
Husum-based environmental consultancy. Homepage markets onshore services including Gutachten (expert opinions), faunistische Erfassungen (fauna surveys), Fledermaus-Höhenmonitoring bei Windenergievorhaben (bat altitude monitoring for wind projects) and Umweltbaubegleitung (environmental construction supervision) — the bat-survey work BImSchG dossiers require.
bioconsult-sh.de
Oldenburg-based planning office. Homepage markets faunistische und floristische Grundlagenerfassung (fauna and flora baseline surveys), Erstellung komplexer Genehmigungsanträge (drafting complex permit applications), fachgutachterliche Vertretung (expert representation) in Genehmigungs- und Beteiligungsverfahren and Umweltbaubegleitung — full developer-side BImSchG dossier capacity.
ibl-umweltplanung.de
Oldenburg-based environmental and regional-planning consultancy. Homepage markets Umweltgutachten für Genehmigungsverfahren (environmental opinions for permit procedures), Beratung und Verfahrensbegleitung (advice and procedure accompaniment), Planung und Monitoring von Kompensationsmaßnahmen (planning and monitoring of compensation measures) — the kind of capacity Regierungspräsidien also draw on under §2a.
arsu.de

Adjacent vendors were considered. Bosch & Partner (a long-standing wind-permit consultancy) was not catalogued because its homepage failed live verification on the date of writing (TLS certificate problem on www.bosch-partner.de). BBB Umwelttechnik (bbb-umwelt.de) and KohlerNusbaumer (kohlernusbaumer.com) returned DNS-resolution failures and so could not be verified on the date of writing. The Fachagentur Wind und Solar (the federal wind and solar agency), the BDEW (the German energy industry association) and the Regierungspräsidien (state-level case-work authorities) are referenced in section 01 as the federal data source, the trade association and the regulator respectively, not third-party solution providers. Inclusion is not endorsement; this list is a starting point for operators searching for help.

Help us improve this page

Report a mistake — or suggest a new solution

Spot a wrong number, dead source link, missing aspect, broken translation? Or know a vendor we should list as a solution? Tell us. The Director re-checks every report and either updates the page or writes back with a reason.

No tracking. We don't put your email on a list. See privacy policy.

Listed companies — manage your entry. If you are one of the providers above and anything here is wrong, missing, or out of date — or you'd rather not be listed — write to us. Removal within 24 hours; corrections within 7 business days. We do not contact listed companies first; we publish what your own public marketing claims and respond when you reach out. Email contact@aikraft.com.

Operators discussing this

These are real German wind-energy operators talking about this pain in their own words on the Photovoltaikforum (Germany's largest renewable-energy operator board). They are the reason this page exists.

  • «Glaube wer 2026 den WKA-Ausbau nicht signifikant erhöht, der hat den Schuss nicht gehört und/oder will wirklich nicht… Realitätsverweigerung halt. Oder das Land hat halt schon wirklich genug und kann sich aufs repowering beschränken. Bayern wird übrigens bald auch noch anziehen… Genehmigungen und Auktionszuschläge zeigen das ja mittlerweile schon deutlich an.»

    "I reckon anyone who doesn't significantly raise wind-turbine build-out in 2026 has not heard the shot, or really does not want to… plain reality-denial. Or the state already has enough and can limit itself to repowering. Bavaria will pick up soon too… permits and tender awards are clearly showing this now."

    Neuigkeiten zur Windenergie (page 1048) · Photovoltaikforum — running operator news thread opened 14 January 2022; reached page 1048 in April 2026; 5 distinct Betreiber-flagged operators on the sampled page; operator dialogue on Genehmigungen, repowering and Auktionszuschläge directly evidences the permit-cycle pain.

  • «In 2025 wurde bei mir in der Umgebung (NRW) einiges an Windrädern hochgezogen, davor die Jahre auf jeden Fall um einiges weniger… Jetzt frage ich mich nur wie das rein Platztechnisch noch gehen soll das zu toppen. Weil durch die 1000m Abstandsregel wird das jetzt schon echt dünn mit Standorten… Eine Position wo vor 2 Jahren schonmal Plökke eingeschlagen wurden ist wohl hinfällig.»

    "In 2025 a fair number of turbines went up in my area (North Rhine-Westphalia), the years before were definitely a lot less… Now I just wonder how this can still be topped from a pure-space angle. Because of the 1000-metre setback rule, sites are getting really thin already… A spot where stakes were driven in two years ago is probably void now."

    Same thread (page 1048) · Photovoltaikforum — distinct NRW operator describing the second-order squeeze: every site that loses its setback eligibility has to start the BImSchG dossier over from zero, restarting the 25-month clock.

Ad · rail 2
Your banner here
€20/ month
No middlemen, no auction, no algorithm. Cancel any time.
We will personally email you when your banner goes live. We are that bootstrapped.
Buy this ad slot →
PayPal subscription · Cancel any time · 1-month minimum